Кой е online

В момента има 258 посетителя в сайта
Hydrostatic test on the project Reunion is almost done, paint work continues intensively
Понеделник, 19 Декември 2011г.

Reunion power plantOn the project EDF PEI, Reunion the hydrostatic test of the third big tank (volume 14,650m3) finished last week on 15th of December 2011. The water is emptied from the tank to the ocean at the moment and will last approximately 10 calendar days.

Продължение...
 
Parallel activities on 10 tanks in Martinique
Четвъртък, 13 Октомври 2011г.

OKZ HOLDING assures in Martinique designOKZ HOLDING assures in Martinique design, delivery, fabrication and erection of 19 storage tanks including painting. On 11th October 2011 OKZ started erection works in the water tank area and works are thus parallel in all areas. At the same time steel roof structures are assembled in the prefabrication area.

Продължение...
 
Continue with hydrostatic test and paint works on the Reunion project
Неделя, 16 Октомври 2011г.

Reunion power plantOKZ team continues with hydrostatic test of the other tanks on the project of Reunion power plant. On the 8th of September 2011 the hydrostatic test of the second biggest tank (volume of 14,650 m3) started.The tank was filled with the water, taken from first tank, on which the hydrostatic test has finished on the 2nd September 2011.

Продължение...
 
Roof assembly in Vlissingen project
Понеделник, 26 Септември 2011г.

Roof assembly in VlissingenFor its client, Vesta Terminal Flushing B.V., OKZ HOLDING builds 7 steel storage tanks with total volume of 224,000 m3 in Vlissingen, the Netherlands. Progress on the project is significant. Currently, dome roof structures have been gradually assembled and lifted up.

Продължение...
 

Текущи проекти