Crude oil tanks disassembly and new piping installation
Client/Investor:
PERN “Przyjaźń” S.A., PL
Contractor:
OKZ HOLDING sp. z o.o., PL
Location:
Crude Oil Storage Tank Farm Plebanka, Płock, PL
Subject:
Disassembly of three crude oil tanks with auxiliary installations: process piping, water, foam and sewage systems, civil works. Installation of new crude oil piping.
Parameters:
3 x 12,000 m3, 309 t of DN800 pipes
Initiated:
07/2011
Completed:
11/2011
Skaityti daugiau...
Erection of water tank for Dolna Odra Power Plant
Client/Investor:
RAFAKO S.A., PL
Contractor:
OKZ HOLDING sp. z o.o., PL
Location:
Dolna Odra Power Plant, Gryfino, Poland
Subject:
Prefabrication and erection of water tank, emergency drainage
Storage capacity:
1 x 1,490 m3
Initiated:
01/2010
Completed:
08/2011
Skaityti daugiau...
Storage tank erection for demineralized water
Client/Investor:
Grupa LOTOS s.a., Fluor s.a., PLA
Contractor:
OKZ HOLDING Sp. z o.o., PL
Location:
LOTOS refinery, Gdaňsk, Poland
Subject:
Delivery and erection of storage tank for demineralized water
Storage capacity:
1 x 5,000 m3
Initiated:
10/2008
Completed:
06/2009
Skaityti daugiau...
Storage tanks erection in Gdansk, Poland
Client/Investor:
PETRO EnergoRem sp. z o.o., PL/Grupa LOTOS s.a., Fluor s.a., PL
Contractor:
OKZ HOLDING sp. z o.o., PL
Location:
Gdaňsk, Poland
Subject:
Erection of tanks for crude oil, incl. piping, equipment and infrastructure
Storage capacity:
2 x 20,000 m3
Initiated:
08/2008
Completed:
03/2009
Skaityti daugiau...