General reconstruction in Mažeikiai refinery - Project LK-1 |
 |
| Client/Investor: |
AB Mažeikiu Nafta, LT
|
| Contractor: |
UAB OKZ HOLDING Baltija, LT
|
| Location: |
Mažeikiai, Lithuania
|
| Subject: |
Production and assembly of steel structures, technological equipment and piping
|
| Weight: |
Steel structures 180 t, equipment 650 t, piping 3.8 km
|
| Initiated: |
05/2008 |
| Completed: |
03/2009 |
|
|
|
|
Więcej…
|
 |
| Client/Investor: |
Naftobudowa, PL/AB Mažeikiu Nafta, LT |
| Contractor: |
UAB OKZ HOLDING Baltija, LT
|
| Location: |
Mažeikiai, Lithuania
|
| Subject: |
Piping assembly
|
| Weight: |
140 t
|
| Initiated: |
05/2008 |
| Completed: |
11/2008 |
|
|
|
|
Więcej…
|
|
General reconstruction in Mažeikiai refinery - Project LK-2 |
 |
| Client/Investor: |
AB Mažeikiu Nafta, LT
|
| Contractor: |
UAB OKZ HOLDING Baltija, LT
|
| Location: |
Mažeikiai, Lithuania
|
| Subject: |
Production and assembly of steel structures, technological equipment and piping
|
| Weight: |
Steel structures 160 t, equipment 650 t, piping lines 4.6 km
|
| Initiated: |
05/2008 |
| Completed: |
11/2008 |
|
|
|
|
Więcej…
|
|
Steel structures production |
 |
| Client/Investor: |
AB ELGA, LT/Hemel Hempstead Terminal, GBR |
| Contractor: |
UAB OKZ HOLDING Baltija, LT
|
| Location: |
Plunge, Lithuania
|
| Subject: |
Production of steel structures
|
| Weight: |
54 t
|
| Initiated: |
08/2008 |
| Completed: |
10/2008 |
|
|
|
|
Więcej…
|
|
|