Hydrostatic test on the Reunion project is almost done, painting works continue intensively
poniedziałek, 19 grudnia 2011
Odsłony: 670
On December 15, 2011, the hydrostatic test of the third big tank (volume 14,650 m3) was finished on the project EDF PEI, Reunion. The water is currently emptying from the tank to the ocean, which will take approximately 10 days.
Continue with hydrostatic test and paint works on the Reunion project
niedziela, 16 października 2011
Odsłony: 1132
OKZ team continues with hydrostatic test of the other tanks on the project of Reunion power plant. On the 8th of September 2011 the hydrostatic test of the second biggest tank (volume of 14,650 m3) started.The tank was filled with the water, taken from first tank, on which the hydrostatic test has finished on the 2nd September 2011.
OKZ HOLDING assures in Martinique design, delivery, fabrication and erection of 19 storage tanks including painting. On 11th October 2011 OKZ started erection works in the water tank area and works are thus parallel in all areas. At the same time steel roof structures are assembled in the prefabrication area.
For its client, Vesta Terminal Flushing B.V., OKZ HOLDING builds 7 steel storage tanks with total volume of 224,000 m3 in Vlissingen, the Netherlands. Progress on the project is significant. Currently, dome roof structures have been gradually assembled and lifted up.
OKZ HOLDING is finalizing works on the project ETT 3 for Verwater Tankbouw B.V. in Rotterdam, the Netherlands. OKZ has assured erection of 6 vertical above ground cylindrical steel storage tanks with aluminium roof for heavy fuel with a volume of 41,500 m3 each.